Regional Transportation District – Replacement of Supply Air Units

Contract With/Owner:

Contract:

Completion Year:

Regional Transportation District

$1,394,116

2010

Removal and replacement of existing 54,000 cfm supply air units with new units.  Included associated welded steam coil piping, electrical, temperature controls, sheet metal, test and balance and commissioning.  All work was completed while the facility was in use.