Municipal Facilities

Municipal Facilities

Aurora Water Meter Replacement

Contract With/Owner: City of Aurora, Colorado
Completion Year: 2002

Replaced more than 200 water meters and vaults.

Denver Permit Center Renovation

Contract With: Panattoni Construction
Owner: City & County of Denver
Contract Amount: $1,121,380

Plumbing upgrade included ADA restroom renovations and complete renovation of the entire mechanical systems on all four floors.  Replaced all the major mechanical equipment and associated piping and sheet metal, test and balance and commissioning.

Fitzsimmons Complex Pool System

Contract With: W.M. Brown Construction
Owner: City of Aurora
Contract Amount: $512,428

Pool Air Handling Unit, 2 boilers, pumps, pool filtration system.

Centennial Gardens Fountain

Contract With: J.C. Brooks & Co.
Owner: City of Denver, Botanic Gardens
Contract Amount: $301,273

Complicated piping of sophisticated fountain.

La Junta City Hall

Contract With/Owner: City of La Junta, Colorado
Contract Amount: $179,394

Chiller replacement.