OLD – Airports

Airports

DIA Central Utility Plant Chillers

Contract With: Trautman & Shreve (Hensel-Phelps)
Owner: Denver International Airport
Contract Amount: $3,548,485

This was a mechanical piping and chiller replacement in the Central Utility Plant at Denver International Airport.

DIA Temporary Boiler

Contract With: Bosco Constructors
Owner: Denver International Airport
Contract Amount: $284,770
Completion Year: 2015

Installed heating water and natural gas piping to a 75,000 MBTUH boiler.

DIA Hydronic Optimization

Contract With: Trautman & Shreve
Owner: Denver International Airport
Contract Amount: $893,000
Completion Year: 2013

Removed all Tertiary building pumps and proprietary BRDG-TNDR controls.  Installed new independent pressure valves at each air handling unit in place of each tertiary pump and at select heating water pumps.  The controls for each air handling unit and each secondary building pump were modified for the control sequences.

Jefferson County Airport - Air Tanker Base

Contract With: FCI, Inc.
Owner: United States Forest Service
Contract Amount: $266,810
Completion Year: 2003
Safety: 0 Lost Days
JCOR Direct Work: 100%

Installed piping system and 1000 gallon water and slurry tanks for slurry bomber use (plumbing).

DIA Central Utility Plant Chiller Addition

Contract With: Bosco Constructors
Owner: Denver International Airport
Contract Amount: $1,630,757
Completion Year: 2014

Installation of two new 2,500 ton chillers in Central Utility Plant Basement.  JCOR’s work included subcontractors – insulation, millwright, water treatment, test, and balance.

DIA UPS Addition

Contract With: Spectrum Construction
Owner: Denver International Airport
Contract Amount: $55,718
Completion Year: 2008
Safety: 0 Lost Days
JCOR Direct Work: 100%

DIA UPS (Uninterrupted Power Source) Addition: Installed a cooling fan coil unit for a UPS room at DIA. Included hot tapping the existing cooling mains and all associated chilled water piping, exhaust fans, and ductwork.