Educational Facilities
DPS Lincoln Boiler Replacement and Science lab renovations
Contract With: | Mark Young Construction |
Owner: | Denver Public Schools |
Contract Amount: | $1,289,909 |
Completion Year: | 2015 |
Furnished and installed (3) 6 million BTU hot water boilers. Work included the associated piping, flue, controls and insulation. JCOR renovated the mechanical and plumbing systems in the science classrooms. Included new mechanical equipment and all acid waste and vent, natural gas, and domestic hot and cold water, and fume hood exhaust.
East High YCC Plumbing and Mechanical
Contract With: | Mark Young Construction |
Owner: | Denver Public Schools |
Contract Amount: | $95,204 |
Completion Year: | 2015 |
JCOR performed the plumbing and mechanical work for the new robotics lab at East HS.
DPS Lincoln Pool Renovation
Contract With/Owner | Denver Public Schools |
Contract Amount: | $313,760 |
Completion Year: | 2014 |
Renovate Pool Piping and Equipment at Abe Lincoln High School.
UCD CUP Expansion 4 Chiller
Contract With/Owner | State of Colorado, University of Colorado |
Contract Amount: | $1,243,240 |
Completion Year: | 2013 |
Scope included adding one chiller and two cooling towers with associated piping and equipment. Work included electrical, sheet metal, structural steel, roofing, insulation, T&B, etc. Occupied during construction.
CU Stearns West Restroom Renovation
Contract With/Owner | State of Colorado, University of Colorado |
Contract Amount: | $125,148 |
Completion Year: | 2013 |
Plumbing for renovation of 27 student restrooms in the dormitory. Re-piped and replaced all of the fixtures.
CU Stearns Tower Mechanical Upgrades
Contract With/Owner | Colorado University Boulder |
Contract Amount: | $238,052 |
Completion Year: | 2011 |
Fast tracked project which included installing approximately 300 shutoff valves on the chilled and hot water risers serving residence towers at Williams Village. Project also included replacing 12 fan coil units.
UCB – Smart Grid Steam Meter Project
Contract With/Owner | Colorado University Boulder |
Contract Amount: | $376,877 |
Completion Year: | 2011 |
Pilot program for a campus-wide sub-metering program. Installed various sizes of high-pressure steam, electrical and domestic water meters. All meters were tied into the campus communication system enabling the meters to be read remotely from a central location.
Wheat Ridge Middle School Improvements
Contract With: | M. W. Golden |
Owner: | Jefferson County School District |
Contract Amount: | $286,003 |
Completion Year: | 2010 |
Installed new owner-provided chiller and a cooling tower with associated piping and six new pumps.
Crown Point Academy (Charter School)
Contract With/Owner: | JHL Constructors |
Contract Amount: | $32,405 |
Completion Year: | 2010 |
A new ground up 45,000 square-foot elementary charter school. JCOR assisted in the design and built the new plumbing systems.
Crown Point Academy (Charter School)
Contract With/Owner: | JHL Constructors |
Contract Amount: | $32,405 |
Completion Year: | 2010 |
A new ground-up 45,000 square-foot elementary charter school. JCOR assisted in the design and built the new plumbing systems.
AIMS Community College Court – HVAC Upgrades Phases I & II
Contract With/Owner: | Aims Community College |
Contract Amount: | $761,987 |
Completion Year: | 2009 |
Complete renovation of the entire mechanical system which included removing the entire dual duct system and replacing it with a single duct hot water VAV system. Included all major mechanical equipment with the associated piping and ductwork, structural steel modifications, temperature controls, test and balancing, and commissioning. All work was completed while the school was occupied.
Rocky Ford High School Mechanical Upgrades
Contract With | Walrath Heating & Air Conditioning |
Owner: | Rocky Ford School District |
Contract Amount: | $258,179 |
Completion Year: | 2007 |
Various mechanical and energy-efficient upgrades including instantaneous water heaters, heating water pumps, rerouting heating water mains, and repiping air handling coils.
Thomas Jefferson, McKinley-Thatcher, Smiley Middle School – Complete HVAC Retrofit
Contract With | Brown Schrepferman Construction |
Owner: | Denver Public Schools |
Contract Amount: | $1,245,480 |
Completion Year: | 2006 |
New steam boiler, 3 high-efficiency hot water heaters, temperature control retrofit from pneumatic to DDC; replaced existing chiller with 135-ton chiller and associated pumps and equipment.
Montclair Elementary School Steam Boilers
Contract With/Owner: | Denver Public Schools |
Contract Amount: | $219,700 |
Completion Year: | 2006 |
Replaced two steam boilers at Montclair Elementary.
South High Water Heater Replacement
Contract With/Owner: | Denver Public Schools |
Contract Amount: | $133,520 |
Completion Year: | 2005 |
Replaced the existing steam to the hot water heat exchanger, removed existing 1500 gallon hot water storage tank, and replaced with three high-efficiency Aerco water heaters.
CSM Mechanical Upgrade
Contract With/Owner: | Colorado School of Mines |
Contract Amount: | $126,157 |
Completion Year: | 2005 |
Chilled Water Distribution -- Added chilled water piping, pumps, and coils to six existing air handlers.
CU-Boulder – Newton Court
Contract With/Owner: | University of Colorado |
Contract Amount: | $145,785 |
Completion Year: | 2002 |
Boiler retrofit.
East High School Boiler Replacement and Science Lab Renovation
Contract With: | Mark Young Construction |
Owner: | Denver Public Schools |
Contract Amount: | $1,182,818 |
Completion Year: | 2015 |
Removed (3) existing steam boilers and replaced them with (4) new 4.8 million BTU steam boilers. Work included new piping, flue, controls and insulation. JCOR renovated the mechanical and plumbing systems in the science classrooms. Included new mechanical equipment and all acid waste and vent, compressed air, natural gas, and domestic hot and cold water, and fume hood exhaust
CU Williams Village Grey Water
Contract With/Owner | State of Colorado, University of Colorado |
Contract Amount: | $107,250 |
Completion Year: | 2015 |
Installed gray water recirculation system at Village North residence hall.
UCD Bldg 400 Steam
Contract With/Owner | State of Colorado, University of Colorado |
Contract Amount: | $359,220 |
Completion Year: | 2014 |
Re-route steam to 400 Series Buildings
UCD Utility Vault 3.2 Emergency Replacement
Contract With/Owner | State of Colorado, University of Colorado |
Contract Amount: | $207,350 |
Completion Year: | 2014 |
Plumbing for renovation of 27 student restrooms in the dormitory. Re-piped and replPhase #1 – Demo’d existing steam vault and replaced steam, condensate, chilled water supply and chilled water return piping with new pre-insulated piping.
Phase #2 – Removed and replaced steam and condensate lines to Buildings 401 and 402. aced all of the fixtures.
CU Stearns Fan Coil Replacement
Contract With/Owner | State of Colorado, University of Colorado |
Contract Amount: | $207,350 |
Completion Year: | 2014 |
Replaced fan coil units in 375 rooms. This short-timeframe project required extensive coordination and complex scheduling. Work included electrical, temperature controls, replacing tile and HVAC.
Highline Academy (Charter School)
Contract With/Owner | JHL Constructors |
Contract Amount: | $278,222 |
Completion Year: | 2011 |
40,000 square foot charter school. The school took possession of an old General Motors Test Facility. JCOR assisted in the design build of the plumbing systems.
Green Mountain High School Boiler Replacement
Contract With/Owner | Jefferson County School District |
Contract Amount: | $114,985 |
Completion Year: | 2011 |
Furnished and installed two new 2,000,000 BTU boilers with the associated welded piping, pumps, flue, piping, electrical controls and insulation.
North Star Academy (Charter School)
Contract With/Owner | JHL Constructors |
Contract Amount: | $314,518 |
Completion Year: | 2010 |
A new design-build 40,000 square foot charter school. The school took possession of an out-of-business 80,000 square foot hardware retail box store. A new elementary school was built in half of the building. JCOR assisted in the design and built the plumbing systems.
Monarch Montessori (Charter School)
Contract With/Owner | JHL Constructors |
Contract Amount: | $181,578 |
Completion Year: | 2010 |
A new 15,000 square foot Montessori school. The school took possession of a portion of the existing office space. JCOR assisted in the design of and built the new plumbing systems. In addition, JCOR troubleshot and repaired the existing heating and cooling systems to get them working properly for the entire building.
Auraria Higher Education Center UPS & Cooling Unit
Contract With/Owner | Auraria Higher Education Center |
Contract Amount: | $457,710 |
Completion Year: | 2009 |
A mechanical prime project which included furnishing and installing a new UPS, Chillers, CRAC unit with all associated chilled water piping, structural support, roofing, temperature controls, insulation, electrical and balancing.
CU MSSC RL-6 Air Handling & Cooling Retrofit
Contract With/Owner: | University of Colorado, Boulder |
Contract Amount: | $329,714 |
Completion Year: | 2008 |
Furnished and installed a new 100-ton chiller and AHU with all associated chilled water piping, structural support, roofing, temperature controls, ductwork, insulation, electrical, and balancing.
Deer Creek, Manning, & Stober Schools – Grease Interceptors
Contract With/Owner: | Jefferson County Public School District |
Contract Amount: | $148,500 |
Completion Year: | 2007 |
Separated grease waste from the sanitary waste inside the kitchen area, ran grease waste through new grease interceptors and tied back into the existing sanitary.
UNC Michener Hall Cooling Tower Replacement
Contract With/Owner: | University of Northern Colorado |
Contract Amount: | $120,500 |
Completion Year: | 2006 |
Replaced and upgraded the existing cooling tower.
Holm, Henry & Dennison Public Schools – Mechanical Retrofit
Contract With: | J.L. Williams |
Owner: | Denver Public Schools |
Contract Amount: | $434,146 |
Completion Year: | 2006 |
Installed new burners on the existing steam boilers, refurbished the existing cooling towers, installed backflow prevention at the water entry, and upgraded the pneumatic controls to DDC at Dennison.
East High School and Lake Middle School – Boiler Burner Replacement
Contract With/Owner: | Denver Public Schools |
Contract Amount: | $314,830 |
Completion Year: | 2005 |
Hydronic System Replacement Hydronic system tie-in.
CU Marine Court – Hydronic System Replacement
Contract With/Owner: | University of Colorado |
Contract Amount: | $118,000 |
Completion Year: | 2005 |
Hydronic System Replacement Hydronic system tie-in.